File #: 0489-20    Version: 1 Name: Change Order No. 2 Town Branch WWTP Thickening Process Upgrades
Type: Resolution Status: Approved
File created: 5/18/2020 In control: Urban County Council
On agenda: 6/11/2020 Final action: 6/11/2020
Enactment date: 6/11/2020 Enactment #: R-254-2020
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Dugan & Meyers, LLC, for the Town Branch Waste Water Treatment Plant Thickening Process Upgrades, increasing the contract price by the sum of $44,286, from $3,261,032 to $3,305,318. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. CO #2 TB Thickener Project Supporting Information, 4. 00686026.pdf, 5. R-254-2020
Related files: 1280-18
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Dugan & Meyers, LLC, for the Town Branch Waste Water Treatment Plant Thickening Process Upgrades, increasing the contract price by the sum of $44,286, from $3,261,032 to $3,305,318. [Div. of Water Quality, Martin]

Summary
Authorization to execute Change Order No. 2 to the Agreement with Dugan & Meyers, LLC, for the Town Branch Waste Water Treatment Plant Thickening Process Upgrades, increasing the Contract price by the sum of $44,286.00, from $3,261,032.00 to $3,305,318.00. Budget Amendment in process. (L0489-20) (Martin/Albright)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Yes, Completed by [Michael Cravens, 5/15/20]}
Risk Management: {NO}
Fully Budgeted [select]: Partial, Budget amendment in process
Account Number: 4003-303401-3401-92711
This Fiscal Year Impact: $44,286.00
Annual Impact: $
Project: TBWWTP_RMP
Activity: CONSENT_DE
Budget Reference:
Current Balance: $34,404.20 and BA in process
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Agreement with Dugan & Meyers, LLC, for the Town Branch Waste Water Treatment Plant Thickening Process Upgrades, increasing the Contract price by the sum of $44,286.00, from $3,261,032.00 to $3,305,318.00.
Section 2 - That an amount, not to exceed the sum of $44,286.00, be and hereby is approved for payment to Dugan & Meyers, LLC, from account # 4003 - 303401 - 92711, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.