header-left
File #: 1237-23    Version: 2 Name: Request Council authorization to execute Change Order No. 9 with ATS Construction for work on Town Branch Trail Phase 6. Change order is for $451,896.42 and will increase the contract to $6,144,424.79. This change order is being submitted concurrently to
Type: Resolution Status: Approved
File created: 11/27/2023 In control: Urban County Council
On agenda: 12/7/2023 Final action: 12/7/2023
Enactment date: 12/7/2023 Enactment #: R-676-2023
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 9 to the Agreement with ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $451,896.42 and raising the total Contract price to $6,144,424.79. [Div. of Engineering, Burton]
Attachments: 1. 24-Blue Sheet ATS CO No.pdf, 2. TBT 6 - LFUCG CO No. 9_for Mayor Signature, 3. Area Map TBT Phase 6, 4. 00801168.pdf, 5. R-676-2023, 6. Contract #003-2023
Related files: 0057-20
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 9 to the Agreement with ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $451,896.42 and raising the total Contract price to $6,144,424.79. [Div. of Engineering, Burton]
Summary
Authorization to execute Change Order No. 9 with ATS Construction for work on Town Branch Trail Phase 6. Change order is for $451,896.42 and will increase the Contract to $6,144,424.79. This Change Order is being submitted concurrently to KYTC. The approval of Change Order No. 9 by LFUCG is contingent on approval by KYTC. Funds are Budgeted. (L1237-23) (Burton/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Ashleigh Bailey, 11/22/2023
Risk Management: N/A
Fully Budgeted: Grant Budget Adjustment in process
Account Number: 3160-303202-3225-90313
This Fiscal Year Impact: $451,896.42
Annual Impact: $0
Project: TOWN_TGER_2017
Activity: CONST
Budget Reference: 2017
Current Balance: Grant Budget Adjustment in process
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
9, which is attached hereto and incorporated herein by reference, to the Agreement with ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $451,896.42 and raising the total Contract price to $6,144,424.79.
Section 2 - That an amount, not to exceed the sum of $451,896.42, is hereby authorized for payment to ATS Construction, from account # 3160-303202-90313, pursuant to the terms of Change Order 9.
Section 3 - That this Resolution shall become effective on the date of its passage.