File #: 0831-26    Version: 1 Name: Whitney Young Change Order #2
Type: Agenda Item Status: Agenda Ready
File created: 9/16/2026 In control: Parks and Recreation
On agenda: 10/6/2026 Final action:
Enactment date: Enactment #:
Title: Authorization to execute change order #2 with Elaine Allen LLC, for the Whitney Young community building renovation project for additional work needed to refinish the restroom floors, increasing the contract by $5,779.01, bringing the new contract total to $253,698.38. Funds are budgeted. (L0831-26) (Conrad/Ford)
Attachments: 1. Change Order 2 Cover Memo Whitney Young Signed with Corrections 3, 2. Whitney Young CO2 Packet Signed with Correction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Authorization to execute change order #2 with Elaine Allen LLC, for the Whitney Young community building renovation project for additional work needed to refinish the restroom floors, increasing the contract by $5,779.01, bringing the new contract total to $253,698.38. Funds are budgeted. (L0831-26) (Conrad/Ford)

 

Summary

Authorization to execute change order #2 with Elaine Allen LLC, for the Whitney Young community building renovation project for additional work needed to refinish the restroom floors, increasing the contract by $5,779.01, bringing the new contract total to $253,698.38. Funds are budgeted. (L0831-26) (Conrad/Ford)

 

Budgetary Implications [select]: Yes

Advance Document Review:

Law: No

Risk Management:  No

Fully Budgeted [select]: Yes

Account Number: 1148-707602-7221-91012

This Fiscal Year Impact: $5,779.01

Annual Impact: No

Project: GSPK_WHITNEY_YG

Activity:

Budget Reference:

Current Balance: $48,918.23

Body