File #: 0622-21    Version: 1 Name: CO No. 1 Investigation and Design West Hickman Solids Processing Building Improvements
Type: Resolution Status: Approved
File created: 6/14/2021 In control: Urban County Council
On agenda: 7/6/2021 Final action: 7/6/2021
Enactment date: 7/6/2021 Enactment #: R-376-2021
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with GRW Engineers, Inc., for investigation and design services for the West Hickman Waste Water Treatment Plant Solids Processing Building Improvements Project, increasing the Contract price by the sum of $70,800, from $243,400 to $314,200. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. 00730569.pdf, 4. R-376-2021

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with GRW Engineers, Inc., for investigation and design services for the West Hickman Waste Water Treatment Plant Solids Processing Building Improvements Project, increasing the Contract price by the sum of $70,800, from $243,400 to $314,200. [Div. of Water Quality, Martin]

Summary

Authorization to execute Change Order No. 1 to the Agreement with GRW Engineers, Inc., for Investigation and Design Services for the West Hickman Waste Water Treatment Plant Solids Processing Building Improvements Project, increasing the Contract price by the sum of $70,800.00, from $243,400.00 to $314,200.00. Funds are Budgeted. (L0622-21) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 6/14/21]}

Risk Management:  {No}

Fully Budgeted [select]: Included in FY 22 Mayor’s Proposed Budget

Account Number:                     4003-303401-3401-92711

This Fiscal Year Impact:                     $70,800.00

Annual Impact:                      $

Project: WHWWTP_RMP

Activity: CONSENT_DE

Budget Reference: 2021

Current Balance: $8,000,000.00 in FY22

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with GRW Engineers, Inc., for investigation and design services for the West Hickman Waste Water Treatment Plant Solids Processing Building Improvements Project, increasing the Contract price by the sum of $70,800.00, from $243,400.00 to $314,200.00.

                     Section 2 - That an amount, not to exceed the sum of $70,800.00, be and hereby is approved for payment to GRW Engineers, Inc., from account #4003 - 303401 - 92711, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                              ______________________________

                                                                                                                              MAYOR

 

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

622-21:MSC:X:\Cases\WATER-AIR\21-LE0001\LEG\00730569.DOCX