A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Agreement with Calhoun Construction Services, Inc., for the New Senior and Therapeutic Center Project, increasing the Contract price by the sum of $1,132,447.13, from $15,428,572.78 to $16,561,019.91. [Dept. of General Services, Ford]
Summary
Authorization to execute Change Order #3 with Calhoun Construction for the New Senior & Therapeutic Center in the amount of $1,132,447.13 increasing the Contract from $15,428,572.78 to $16,561,019.91 with a (0) calendar day change to the Contract time for the remediation of unsuitable soils. Funds are Budgeted. (L0439-25)(Ford)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Select Yes/No, Completed by [Attorney Name, Date]}
Risk Management: {Select Yes/No, Completed by [Official, Date]}
Fully Budgeted [select]: Yes
Account Number: 2615-606102-6051-90511
This Fiscal Year Impact: $1,132,447.13
Annual Impact: $
Project: SRTHER_CTR_2025
Activity: CONSTRUCT_CAP
Budget Reference: 2025
Current Balance: $8,220,174.99
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 3, which is attached hereto and incorporated herein by reference, to the Agreement with Calhoun Construction Services, Inc., for the New Senior and Therapeutic Center Project, increasing the Contract price by the sum of $1,132,447.13, from $15,428,572.78 to $16,561,019.91.
Section 2 - That an amount, not to exceed the sum of $1,132,447.13, be and hereby is approved for payment to Calhoun Construction Services, Inc., from account # 2615-606102-90511, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.