Title
A Resolution authorizing the Mayor, on behalf of the Lexington-Fayette Urban County Government, to execute Change Order No. 1 to the Contract with Central Bridge Co., LLC, for the Brighton Rail Trail Project, increasing the Contract price by $123,526.65 and raising the total Contract price from $2,854,768.01 to $2,978,294.66. [Div. of Engineering, Burton]
Summary
Authorization to execute Change Order No.1 with Central Bridge Company, LLC for the Brighton Rail Trail Bridge Project, increasing the Contract price by the sum of $123,526.65 from $2,854,768.01 to $2,978,294.66. Funds are Budgeted. (L0014-22) (Burton/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Brittany Smith, 12/28/2021
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 3160-303202-3225-90313
This Fiscal Year Impact: $123,526.65
Annual Impact: $0
Project: BRIGHTON_2017
Activity: CONSTRUCT
Budget Reference: 2017
Current Balance: $280,045.09
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Contract with Central Bridge Company, LLC, for the Brighton Rail Trail Project, increasing the contract price by $123,526.65, and raising the total contract price from $2,854,768.01 to $2,978,294.66.
Section 2 - That an amount, not to exceed a sum of $123,526.65, is hereby authorized for payment to Central Bridge Company, LLC, from account # 3160-303202-3225-90313, pursuant to the terms of Change Order No. 1.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: