A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Agreement with The Allen Co., Inc., for the Elizabeth Street and Forest Park Site Improvements Project, decreasing the contract price by the sum of $17,166.49, from $179,185.10 to $162,018.61. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No. 1 (Final) to the Agreement with The Allen Company, Inc., for the Elizabeth Street and Forest Park Site Improvements Project, decreasing the Contract price by the sum of $17,166.49, from $179,185.10 to $162,018.61. (L0869-20) (Martin/Albright)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Yes, Completed by [Michael Cravens, 9/2/20]}
Risk Management: {No}
Fully Budgeted [select]: Yes
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $-17,166.49
Annual Impact: $
Project: ELIZFOREST_2020
Activity: CONSTRUCT
Budget Reference: 2020
Current Balance: $28,614.90
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with The Allen Company, Inc., for the Elizabeth Street and Forest Park Site Improvements Project, decreasing the contract price by the sum of $17,166.49, from $179,185.10 to $162,018.61.