File #: 0100-19    Version: 1 Name: Town Branch Digester C/O #1
Type: Resolution Status: Approved
File created: 1/24/2019 In control: Urban County Council
On agenda: 3/7/2019 Final action: 3/7/2019
Enactment date: 3/7/2019 Enactment #: R-097-2019
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Judy Construction Co., for the Town Branch Waste Water Treatment Plant Primary Digester Complex Improvements Project, increasing the Contract price by the sum of $53,958.58, from $9,746,750.00 to $9,800,708.58. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo.pdf, 2. Change Order Proposal Documents from Judy Constrution.pdf, 3. 00643011.pdf, 4. RESOLUTION - 097-2019, 5. 025-2018 CONTRACT, 6. Contract #025-2018

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Judy Construction Co., for the Town Branch Waste Water Treatment Plant Primary Digester Complex Improvements Project, increasing the Contract price by the sum of $53,958.58, from $9,746,750.00 to $9,800,708.58. [Div. of Water Quality, Martin]

 

Summary

Authorization for approval of Change Order #1 to the Contract with Judy Construction Company for the Town Branch WWTP Digester Complex Improvements. Approval of this Change Order results in an increase of $53,958.58 to the original Contract. The revised Contract amount including this Change Order will be $9,800,708.58 representing a 0.55% increase of the original Contract amount. Funds are Budgeted. (L0100-19) (Martin)

Budgetary Implications: Yes

Advance Document Review:

Law: Yes, Completed by Michael Cravens, 1/25/2019

Risk Management:  No

Fully Budgeted: Yes                                                               

Account Number:                     4003-303401-3401-92711

This Fiscal Year Impact:                     $53,958.58

Annual Impact:                      $0.00

Project: TBWWTPDIGES_RMP

Activity: CONSEDNT_DE

Budget Reference: 2017

Current Balance: $758,134.69

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Judy Construction Company, for the Town Branch Waste Water Treatment Plant Primary Digester Complex Improvements Project, increasing the contract price by the sum of $53,958.58, from $9,746,750.00 to $9,800,708.58.

                     Section 2 - That an amount, not to exceed the sum of $53,958.58, be and hereby is approved for payment to Judy Construction Company, from account #4003 -  303401 - 92711, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL: