File #: 0321-16    Version: 1 Name: Change Order Resolution for Olympic Construction, LLC for the Fire Station #2 Construction
Type: Resolution Status: Approved
File created: 3/22/2016 In control: Urban County Council
On agenda: 4/21/2016 Final action: 4/21/2016
Enactment date: 4/21/2016 Enactment #: R-221-2016
Title: A Resolution authorizing the Mayor or his designee, on behalf of the Urban County Government, to execute certain Change Orders meeting the criteria provided in this Resolution, to the Contract with Olympic Construction, LLC, for the construction of Fire Station No. 2. [Div. of Facilities and Fleet Management, Baradaran]
Attachments: 1. Change Order Resolution Memorandum.pdf, 2. R 038-2016.pdf, 3. 00527915.pdf, 4. RESOLUTION - 221-2016.pdf, 5. Change Order #1, 6. Change Order #2, 7. 13-2016 CONTRACT.pdf, 8. 013-2016 -CONTRACT - CO#2.pdf, 9. 013-2016 - CONTRACT - CO #6.pdf, 10. 013-2016 CONTRACT.pdf, 11. 013-2016 CONTRACT.pdf, 12. 013-2016 - CONTRACT.pdf, 13. 013-2016 - CONTRACT.pdf, 14. 013-2016 CONTRACT.pdf, 15. 013-2016 - CONTRACT(1).pdf, 16. 013-2016 CONTRACT.pdf
Title
A Resolution authorizing the Mayor or his designee, on behalf of the Urban County Government, to execute certain Change Orders meeting the criteria provided in this Resolution, to the Contract with Olympic Construction, LLC, for the construction of Fire Station No. 2. [Div. of Facilities and Fleet Management, Baradaran]
Summary
Authorization for the Mayor or his designee, on behalf of the Urban County Government, to execute certain Change Orders meeting the criteria provided in this Resolution, to the contract with Olympic Construction, LLC, for the Construction of Fire Station #2. (L0321-16) (Baradaran/Reed)
Budgetary Implications [select]: NO
Advance Document Review:
Law: { Yes, Completed by [David Barberie, 3/21/16}
Risk Management: {No}
Fully Budgeted [select]:
Account Number:
This Fiscal Year Impact: $
Annual Impact: $
Project:
Activity:
Budget Reference:
Current Balance:
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That in order to ensure the timely completion of the construction of Fire Station No. 2, the Mayor or his designee, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute any necessary Change Orders to the contract with Olympic Construction, LLC, for the construction of Fire Station No. 2, as long as such Change Orders meet the criteria provided in this Resolution.
Section 2 - (a) All Change Orders will be reviewed and recommended by the consulting architect, Brandstetter Carroll, Inc. (or their sub-consultants), and by the Urban County Government's Project Manager, Division of Purchasing, and Commissioner of General Services to assure need, appropriateness and accuracy.
(b) The reviews and recommendations will be conducted prior to submittal of such Change Orders to the Mayor or his designee for signature.
(c) A summary of all Change Orders executed pursuant to this Resolution shall be ...