File #: 0293-26    Version: 1 Name: Change Order No.1 NE Pump Station Banks Engineering Inc.
Type: Agenda Item Status: Agenda Ready
File created: 4/8/2026 In control: Water Quality
On agenda: 4/21/2026 Final action:
Enactment date: Enactment #:
Title: Authorization to approve Change Order No.1 for Future North Elkhorn Pump Station Survey & Easement Services (R-493-2025). Increasing the contract amount with Banks Engineering Inc. by $4,500 from $37,900 to $42,400. Funds are budgeted. (L0293-26)(Sanders/Martin)
Attachments: 1. Blue Sheet Memo, 2. Banks Proposal, 3. Change Order Contract, 4. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Authorization to approve Change Order No.1 for Future North Elkhorn Pump Station Survey & Easement Services (R-493-2025). Increasing the contract amount with Banks Engineering Inc. by $4,500 from $37,900 to $42,400. Funds are budgeted. (L0293-26)(Sanders/Martin)

Summary

Authorization to approve Change Order No.1 for Future North Elkhorn Pump Station Survey & Easement Services (R-493-2025). Increasing the contract amount with Banks Engineering Inc. by $4,500 from $37,900 to $42,400. Funds are budgeted. (L0293-26)(Sanders/Martin)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: Yes  Todd Henning  4/08/26

Risk Management: No

Fully Budgeted [select]: Yes

Account Number:                     4003-303408-3466-92811

This Fiscal Year Impact:                     $4,500.00

Annual Impact: $

Project: PWSW_NEPSTANK26

Activity: CONSENT_DE

Budget Reference:

Current Balance: $18,505,000.00