Title
Authorization to approve Change Order No.1 for Future North Elkhorn Pump Station Survey & Easement Services (R-493-2025). Increasing the contract amount with Banks Engineering Inc. by $4,500 from $37,900 to $42,400. Funds are budgeted. (L0293-26)(Sanders/Martin)
Summary
Authorization to approve Change Order No.1 for Future North Elkhorn Pump Station Survey & Easement Services (R-493-2025). Increasing the contract amount with Banks Engineering Inc. by $4,500 from $37,900 to $42,400. Funds are budgeted. (L0293-26)(Sanders/Martin)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: Yes Todd Henning 4/08/26
Risk Management: No
Fully Budgeted [select]: Yes
Account Number: 4003-303408-3466-92811
This Fiscal Year Impact: $4,500.00
Annual Impact: $
Project: PWSW_NEPSTANK26
Activity: CONSENT_DE
Budget Reference:
Current Balance: $18,505,000.00
Body
{COUNCIL CLERK’S OFFICE WILL COMPLETE - Body of resolution or ordinance}