A Resolution authorizing the Mayor, on behalf of the Lexington-Fayette Urban County Government, to execute Change Order No. 2 to the Agreements with Tetra Tech, Inc., for the Former Jacks Creek Pike Landfill Improvement Project, for the Div. of Water Quality, decreasing the Contract price by the collective sum of $36,900, from $156,350 to $119,450. [Div. of Environmental Services, Carey]
Summary
Authorization to approve Change Order No. 2 (final) with Tetra Tech, Inc., for the Former Jacks Creek Pike Landfill Improvement Project, reducing the amount Budgeted by $36,900.00 due to savings from onsite oversight, making a total amended Contract amount of $119,450.00. (L0870-24) (Carey/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Chris Eller, August 28, 2024
Risk Management: No
Fully Budgeted: NA
Account Number:
This Fiscal Year Impact: decrease $36,900
Annual Impact: $
Project:
Activity:
Budget Reference:
Current Balance:
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Agreements with Tetra Tech, Inc., for the former Jacks Creek Pike Landfill Improvement Project, for the Division of Water Quality, decreasing the contract price by the collective sum of $36,900.00, from $156,350.00 to $119,450.00.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL
0870-24:CWE:4865-8638-2046, v. 1