header-left
File #: 1232-14    Version: 1 Name: Change Order #3 - Marrillia Design & Construction - Senior Citizen Center project
Type: Resolution Status: Approved
File created: 11/18/2014 In control: Urban County Council
On agenda: 11/20/2014 Final action: 11/20/2014
Enactment date: 11/20/2014 Enactment #: R-679-2014
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to Execute Change Order No. 3 to the Contract with Marrillia Design & Construction, for the Replacement Senior Citizen Center Design Project, increasing the contract price by the sum of $102,869 from $8,882,900 to $8,985,769. [Council Office, Maynard]
Attachments: 1. Memorandum - Change Order #3 - Marrillia Design & Construction.pdf, 2. Change Order #3 - Marrillia Design & Construction.pdf, 3. Justification - Change Order #3 - Marrillia Design & Construction.pdf, 4. Proposal Request - Change Order #3 - Marrillia Design & Construction.pdf, 5. Contract 227-2014 Change Order 3.pdf, 6. Resolution 679-2014.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to Execute Change Order No. 3 to the Contract with Marrillia Design & Construction, for the Replacement Senior Citizen Center Design Project, increasing the contract price by the sum of $102,869 from $8,882,900 to $8,985,769. [Council Office, Maynard]
Summary
Authorization to execute Change Order #3 for Marrillia Design & Construction Contract #227-2014 in the amount of $102,869.00 for the replacement Senior Citizen Center construction project. The new contract total is $8,985,769.00. (L1232-14) (Reed).
This is a request to execute Change Order #3 for Marrillia Design & Construction Contract #227-2014 in the amount of $102,869.00 for the replacement Senior Citizen Center construction project. The new contract total is $8,985,769.00. Funds are budgeted.   
Budgetary Implications: Yes        
Advance Document Review:  Department of Law
Fully Budgeted: Yes    
Account Number(s):       2604 606101 6001 90511      
This Fiscal Year Impact:      $102,869.00
Annual Impact:       NA  
Project:
Activity:
Budget Reference:
Current Balance: $2,975,871.27
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
      Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 3, which is attached hereto and incorporated herein by reference, to the contract with Marrillia Design & Construction for the Replacement Senior Citizen Center Design Project, increasing the contract price by the sum of $102,869.00 from $8,882,900.00 to $8,985,769.00.
      Section 2 - That this Resolution shall become effective on the date of its passage.
      PASSED URBAN COUNTY COUNCIL:
 
 
 
 
                                                                        
                                    MAYOR
 
ATTEST:
 
________________________________
CLERK OF URBAN COUNTY COUNCIL