Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Contract with EOP Architecture, for the replacement Senior Citizen Center Design Contract #8-2014, increasing the contract price by the sum of $5,950 from $158,965 to $164,915. [Dept. of General Services, Reed]
Summary
Authorization to execute Change Order #1 with EOP Architecture for the replacement Senior Citizen Center Design Contract #8-2014. (L0166-14) (Reed)
This is a request to execute Change Order #1 with EOP Architecture for an amount of $5,950.00 for the replacement Senior Citizen Center Design Contract #8-2014. This increase brings the new contract total to $164,915.00. Funds are budgeted.
Budgetary Implications: Yes
Advance Document Review: NA
Fully Budgeted: Yes
Account Number: 2603-606102-6081-90511
This Fiscal Year Impact: $5,950.00
Annual Impact:
Project: SR_CITIZEN_2014
Activity: CONSTRUCT
Budget Reference: 2014
Current Balance: $4,541,035.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. One (1), which is attached hereto and incorporated herein by reference, to the Contract with EOP Architecture for replacement Senior Citizen Center Design Contract # 8-2014, increasing the contract price by the sum of $5,950.00 from $158,965.00 to $164,915.00.
Section 2 - That an amount, not to exceed the sum of $5,950.00, be and hereby is approved for payment to EOP Architecture from account 2603-606102-90511, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL