Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final), to the Contract with E.C. Mathews Co., Inc., for the Rose St. Steam Vault Relocation Project, decreasing the contract price by the sum of $8,642 from $44,800 to $36,158. [Div. of Engineering, Burton]
Summary
Authorization to approve change Order No. 1 (Final) to contract with E.C. Mathews Company, Inc., decreasing total amount by $8,624.00 for a new total of $36,158.00 for the Rose Street Steam Vault Relocation Project. (L0601-16) (Burton/Paulsen)
Budgetary Implications: Yes
Fully Budgeted: Yes
Account Number: 3160-303202-3225-90313
This Fiscal Year Impact: ($8,642.00)
Annual Impact: $
Project: ROSESTBK_2008
Activity: FED_GRANT
Budget Reference: 2008
Current Balance:
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1 (FINAL), which are attached hereto and incorporated herein by reference, to the Contract with E.C. Mathews Company, Inc., for the Rose Street Steam Vault Relocation Project, decreasing the contract price by the sum of $8,642.00 from $44,800.00 to $36,158.00.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL