header-left
File #: 1103-23    Version: 1 Name: Consultant Services Agreement- New Senior & Therapeutic Center - EOP Architects
Type: Resolution Status: Approved
File created: 10/20/2023 In control: Urban County Council
On agenda: 11/2/2023 Final action: 11/2/2023
Enactment date: 11/2/2023 Enactment #: R-605-2023
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute a Consultant Services Agreement (awarded pursuant to RFP No. 40-2023), with Champlin/Haupt Architects Inc. d/b/a EOP Architects, for professional design services of the New Senior & Therapeutic Center, for the Dept. of General Services, at a cost not to exceed $736,133. [Div. of Facilities and Fleet Management, Baradaran]
Attachments: 1. New Senior Therapeutic Center Design_Memo_EOP, 2. New Senior Therapeutic Center Design_EOP Proposal, 3. New Senior Therapeutic Center Design_EOP_Consultant Contract, 4. New Senior Therapeutic Center Design_RFP_Pkg_40-2023, 5. New Senior Therapeutic Center Design_EOP_Certificate of Insurance, 6. 00798769.pdf, 7. R-605-2023, 8. Contract #305-2023
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute a Consultant Services Agreement (awarded pursuant to RFP No. 40-2023), with Champlin/Haupt Architects Inc. d/b/a EOP Architects, for professional design services of the New Senior & Therapeutic Center, for the Dept. of General Services, at a cost not to exceed $736,133. [Div. of Facilities and Fleet Management, Baradaran]

Summary
Authorization to execute a consultant services Agreement, pursuant to RFP No. 40-2023, with Champlin/Haupt Architects Inc., dba EOP Architects, for professional design services of the New Senior & Therapeutic Center at a cost of $736,133. Funds are Budgeted. (L1103-23) (Baradaran/Ford)

Budgetary Implications [select]: Yes
Advance Document Review:
Law: n/a
Risk Management: n/a
Fully Budgeted [select]: Yes
Account Number: 1105-606102-6051-71206
This Fiscal Year Impact: $736,133
Annual Impact: $0
Project: 2023-SENIOR_CTR_2023
Activity: DESIGN_CAP
Budget Reference: 2023
Current Balance: $1,415,606.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Urban County Government, be and hereby is authorized and directed to execute a Consultant Services Agreement (awarded pursuant to RFP No. 40-2023), which is attached hereto and incorporated herein by reference, with Champlin/Haupt Architects Inc. dba EOP Architects, for professional design services of the New Senior & Therapeutic Center, for the Department of General Services, at a cost not to exceed $736,133,000.00.
Section 2 - That an amount, not to exceed the sum of $736,133.00, be and hereby is approved for payment to Champlin/Haupt Architects Inc. dba EOP Architects, from account # 1105-606102-71206, pursuant to the terms of the Consultant Services Agreement.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:



_____________...