Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Contract with Sensabaugh Design and Construction, for a pole barn storage building, increasing the contract price by the sum of $3,275 from $189,000 to $192,275. [Div. of Police, Bastin]
Summary
Authorization to execute Change Order No. 1 to Agreement with Sensabaugh Design & Construction to complete additional work for the Police Pole Barn Storage Building. (L545-12) (Bastin/Mason)
This is a request to execute Change Order No. 1 to Agreement with Sensabaugh Design & Construction for an amount of $3,275 required to complete additional work for the Police Pole Barn Storage Building. This increase brings the total cost to $192,275. Funds are budgeted.
Budgetary Implications: Yes
Advance Document Review: Law/Risk Management
Fully Budgeted: Yes
Account Number: 1132-505501-5511-91017
This Fiscal Year Impact: $ $3,275
Annual Impact: $
Project:
Activity:
Budget Reference:
Current Balance: 175,000.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. One (1), which is attached hereto and incorporated herein by reference, to the Contract with Sensabaugh Designs and Construction for a pole barn storage building, increasing the contract price by the sum of $3,275.00 from $189,000.00 to $192,275.00.
Section 2 - That an amount, not to exceed the sum of $3,275.00, be and hereby is approved for payment to Sensabaugh Designs and Construction from account # 1132-505501-91017, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL