header-left
File #: 0912-15    Version: 1 Name: Coroner CAC Riddell Construction Change Order #2
Type: Resolution Status: Approved
File created: 6/29/2015 In control: Urban County Council
On agenda: 7/7/2015 Final action: 7/7/2015
Enactment date: 7/7/2015 Enactment #: R-473-2015
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Riddell Construction, Inc., for the Coroner/Community Action Center Renovation Project, extending the performance period by twenty-four (24) work days at no additional cost. [Dept. of General Services, Reed]
Attachments: 1. CAC Coroner Memo, 2. Change Order #2 - Riddell Construction - #338-2014.pdf.pdf, 3. Justification for Change - Riddell Construction CO#2 - #338-2014.pdf.pdf, 4. Documentation for Change - Riddell Construction CO#2 - #338-2014.pdf.pdf, 5. 07-07-15 - RESOLUTION - 473-2015 - - CLK - Ordinances & Resolutions - 07-13-15, 6. C-338-2014 Change Order 2

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Riddell Construction, Inc., for the Coroner/Community Action Center Renovation Project, extending the performance period by twenty-four (24) work days at no additional cost. [Dept. of General Services, Reed]

Summary

Authorization to Execute Change Order #2 with Riddell Construction Inc. for a Time Extension for the Coroner/CAC Renovation Contract #338-2014. The contract total will stay the same at $597,472.38.  The time extension of an additional 24 working days will be added to the project schedule. A total of 24 working days time extension to the contract required due to adverse weather. No funds are needed for this change. (L0912-15)(Reed)

Budgetary Implications [select]: NO

Advance Document Review:

Law: N/A

Risk Management: N/A

Fully Budgeted [select]:

Account Number:                     

This Fiscal Year Impact:                     

Annual Impact:                      

Project:                      

Activity:                      

Budget Reference: 

Current Balance:

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Contract with Riddell Construction, Inc., for the Coroner/Community Action Center Renovation Project, extending the performance period by twenty-four (24) work days at no additional cost to the Lexington-Fayette Urban County Government.

                     Section 2 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

 

 

 

                                                                                                                              ___________________________________

                                                                                                                              MAYOR

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL