A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute the Engineering Services Agreement (awarded pursuant to RFP No. 38-2024) with Hazen and Sawyer PSC, for design and construction management services for the East Hickman Pump Station Expansion and Rehabilitation Project, at a cost not to exceed $312,341. [Div. of Water Quality, Martin]
Summary
Authorization to execute an Engineering Service Agreement with Hazen and Sawyer PSC, pursuant to RFP No. 38-2024, for design and construction management services required for the East Hickman Pump Station Expansion and Rehabilitation project. Cost not to exceed $312,341. Funds are Budgeted. (L0763-24) (Martin/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Ashleigh Bailey, 7/26/2024
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 3230-303408-3466-92811
This Fiscal Year Impact: $312,341
Annual Impact: $0
Project: EHPSP2_2024
Activity: FED_GRANT
Budget Reference: 2024
Current Balance: $2,780,000.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute the Engineering Services Agreement (awarded pursuant to RFP No. 38-2024), which is attached hereto and incorporated herein by reference, with Hazen and Sawyer PSC, for design and construction management services for the East Hickman Pump Station Expansion and Rehabilitation Project.
Section 2 - That an amount, not to exceed the sum of $312,341.00, be and hereby is approved for payment to Hazen and Sawyer PSC, from account # 3230-303408-92811, pursuant to the terms of the Engineering Services Agreement.
Section 3 - This Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: