A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Two (2) (Final) to the Contract with Lexington Quarry Co. for the Southland Dr. Bike Lane Project, decreasing the contract price by the sum of $6,229.71 from $674,194.73 to $667,965.02. [Div. of Grants and Special Programs/Dept. of Planning, Preservation and Development, Gooding/Paulsen]
Summary
Authorization to execute Change Order No. 2 (Final) with Lexington Quarry Company decreasing contract amount for the Southland Drive Bike Lane Project. The decrease will be by $6,229.71 for a new total of $667,965.02. There will be no budgetary impact. (L1335-15)(Gooding/Paulsen)
Budgetary Implications: YES
Advance Document Review: NO
Fully Budgeted YES
Account Number: 1136-303202-3251-91715
This Fiscal Year Impact: ($6,229.71)
Annual Impact: $
Project:
Activity:
Budget Reference:
Current Balance: 1,561,229.12
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. Two (2) (Final), which is attached hereto and incorporated herein by reference, to the Contract with Lexington Quarry Company for the Southland Drive Bike Lane Project, decreasing the contract price by the sum of $6,229.71 from $674,194.73 to $667,965.02.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: