Title
A Resolution authorizing the Div. of Water Quality to purchase Allen-Bradley Automation Equipment to upgrade the blower system at the Town Branch Wastewater Treatment Plant, from CED of Lexington (as distributor for Rockwell Automation), at a cost not to exceed $42,000. [Div. of Water Quality, Martin]
Summary
Authorization to approve the purchase of Allen-Bradley Automation equipment in order to upgrade the Blower Control System located at the Town Branch Wastewater Treatment Plant. (429-11) (Martin/Bush)
This is a request to approve the purchase of Allen-Bradley Automation equipment in order to upgrade the Blower Control System located at the Town Branch Wastewater Treatment Plant at a cost not to exceed $42,000.00. The current control system for these blowers is over 20 years old and needs to be upgraded in order to be compatible with future SCADA (Supervisory Control and Data Acquisition) upgrades. Funds are budgeted.
Budgetary Implications: Yes
Advance Document Review: Law/Risk Management
Fully Budgeted: Yes
Account Number: 4002-303402-0001-91017
This Fiscal Year Impact: $42,000.00
Annual Impact: None
Project:
Activity:
Budget Reference:
Current Balance: $624,888.64