Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 8 to the Agreement with Marrillia Design and Construction Inc., for the Town Branch Park Access Improvements Project, increasing the Contract price by the sum of $341,948.32, from $5,483,002.00 to $5,824,950.32. [Div. of Engineering, Burton]
Summary
Authorization to execute Change Order No. 8 with Marrillia Design and Construction Inc., in the amount of $341,948.32 for The Town Branch Park Access Improvements Project, bringing the total project cost to $5,824,950.32, to cover several additional work items related to aesthetics, handrail installation, and drainage. Funds are Budgeted. (L1055-25)(Burton/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Michael R. Sanner, November 5, 2025
Risk Management: No
Fully Budgeted: Yes
Account Number: 1105-303202-3251-91715
This Fiscal Year Impact: $341,948.32
Annual Impact: N/A
Project: TB_PARK2_2023
Activity: CONSTRUCT_CAP
Budget Reference: 2023
Current Balance: $1,603,682.15
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 8, which is attached hereto and incorporated herein by reference, to the Agreement with Marrillia Design and Construction Inc., for the Town Branch Park Access Improvements Project, increasing the contract price by the sum of $341,948.32, from $5,483,002.00 to $5,824,950.32.
Section 2 - That an amount, not to exceed the sum of $341,948.32, be and hereby is approved for payment to Marrillia Design and Construction Inc., from account 1105-303202-91715.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
________________________________
MAYOR
ATTEST:
________________________________
C...
Click here for full text