File #: 0257-23    Version: 2 Name: Request Council authorization execute Change Order No.4, with Pace Contracting, for the Splash! at Charles Young Park construction project, for $28,297.75, increasing the contract price by the sum of $28,297.75 from $1,480,048.15 to $1,508,345.90, and ext
Type: Resolution Status: Approved
File created: 2/27/2023 In control: Urban County Council
On agenda: 3/23/2023 Final action: 3/23/2023
Enactment date: 3/23/2023 Enactment #: R-164-2023
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Four (4) to the Agreement with Pace Contracting for the Splash! at Charles Young Park Construction Project, increasing the Contract price by $28,297.75 and raising the total Contract price to $1,508,345.90, and extending the completion deadline to July 3, 2023. [Mayor's Office, Peacher]
Attachments: 1. 23-Bluesheet Memo CO #4 Splash!, 2. CO4_Splash_council form_PACE - Unsigned, 3. 5523 - Splash! - CO#04 Breakdown - Revised 2-27-23, 4. 00776458.pdf, 5. R-164-2023, 6. Change Order #100-2022
Related files: 0444-22
Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Four (4) to the Agreement with Pace Contracting for the Splash! at Charles Young Park Construction Project, increasing the Contract price by $28,297.75 and raising the total Contract price to $1,508,345.90, and extending the completion deadline to July 3, 2023. [Mayor's Office, Peacher]


Summary
Authorization execute Change Order No.4, with Pace Contracting, for the Splash! at Charles Young Park construction project, increasing the Contract price by the sum of $28,297.75 from $1,480,048.15 to $1,508,345.90, and extending the completion deadline to July 3, 2023. Funds are Budgeted. (L0257-23) (Peacher/Scott)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Brittany Smith, 2/27/2023
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 2604 707602 7221 90319 - $6,634.87
3300 707602 7221 90319 - $21,662.88
This Fiscal Year Impact: $28,297.75
Annual Impact: $0
Project: CYNG_PUMP_2014B; BGCF_SPLSH_2023
Activity: CONSTRUCT_CAP; OTH_GRANT1
Budget Reference: 2014 and 2023
Current Balance: 2604 707602 7221 90319 - $6,634.87
3300 707602 7221 90319 - $50,000.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
Four (4), which is attached hereto and incorporated herein by reference, to the Agreement with Pace Contracting for the Splash! at Charles Young Park construction project, increasing the Contract price by $28,297.75 and raising the total Contract price to $1,508,345.90, and extending the completion deadline to July 3, 2023.
Section 2 - That an amount, not to exceed the sum of $28,297.75, is hereby authorized for payment to Pace Contracting, from account # 2604-707602-90319 ($6,634.87) and account # 330...