header-left
File #: 1288-18    Version: 1 Name: Change Order #2 (Final) The Allen Company Wilson Downing Road Drainage Improvements Project
Type: Resolution Status: Approved
File created: 11/26/2018 In control: Urban County Council
On agenda: 12/4/2018 Final action: 12/4/2018
Enactment date: 12/4/2018 Enactment #: R-773-2018
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 (Final) to the Agreement with the Allen Co., Inc., for the Wilson Downing Rd. Drainage Improvements Project, increasing the Contract price by the sum of $12,126.20, from $993,882.50 to $1,006,008.70, and extending the date of completion by twenty-one (21) days, from September 14, 2018 to October 5, 2018. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo.pdf, 2. LFUCG Contract Change Order.pdf, 3. Backup Detail - Final CO2 Wilson Downing Road Drainage Improvements.pdf, 4. Map of Area -Wilson Downing Drainage.pdf, 5. 00635860.pdf, 6. R-773-2018, 7. C-313-2017
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 (Final) to the Agreement with the Allen Co., Inc., for the Wilson Downing Rd. Drainage Improvements Project, increasing the Contract price by the sum of $12,126.20, from $993,882.50 to $1,006,008.70, and extending the date of completion by twenty-one (21) days, from September 14, 2018 to October 5, 2018. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order #2 (Final) to the Agreement with The Allen Company, Inc., for the Wilson Downing Road Drainage Improvements project, increasing the Contract price by the sum of $12,126.20 from $993,882.50 to $1,006,008.70, and extending the Contract completion date by 21 days. Funds are Budgeted. (L1288-18) (Martin)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Yes, Completed by [Michael Cravens, 11/20/18]}
Risk Management: {No}
Fully Budgeted [select]: Yes
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $12,126.20
Annual Impact: $
Project: WILSON_2017
Activity: CONSTRUCT
Budget Reference: 2017
Current Balance: $277,786.12
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with The Allen Company, Inc., for the Wilson Downing Road Drainage Improvements Project, increasing the Contract price by the sum of $12,126.20, from $993,882.50 to $1,006,008.70, and extending the date of completion by twenty-one (21) days, from September 14, 2018 to October 5, 2018.
Section 2 - That an amount, not to exceed the sum of $12,126.20, be and hereby is approved for payment to The Allen Company, Inc., from account # 4052 - 303204 - 92211, pursuant to the terms of the Change Order.
Section 3 - That...

Click here for full text