A Resolution authorizing the Mayor or her designee, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Terracon, for Special Inspections associated with the new Senior and Therapeutic Center construction, increasing the Contract price by the sum of $13,870, from $50,305 to $64,175. [Dept. of General Services, Ford]
Summary
Authorization to execute Change Order #2 with Terracon for Special Inspections associated with soil density testing related to the New Senior & Therapeutic Center construction in the amount of $13,870.00 increasing the Contract amount from $50,305.00 to $64,175.00. Funds are Budgeted. (L0145-26)(Ford)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: N/A
Risk Management: N/A
Fully Budgeted [select]: Yes
Account Number: 1105-606102-6051-71206
This Fiscal Year Impact: $ 13,870
Annual Impact: $0
Project: SENIOR_CTR_2023
Activity: DESIGN_CAP
Budget Reference: 2023
Current Balance: $235,367.71
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor or her designee, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Agreement with Terracon, for special inspections associated with the New Senior & Therapeutic Center construction, increasing the contract price by the sum of $13,870.00, from $50,305.00 to $64,175.00.
Section 2 - That an amount, not to exceed the sum of $13,870.00, be and hereby is approved for payment to Terracon, from the following account 1105-606102-71206, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: