Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Elaine Allen, for replacement of a failed septic system and modifications to walls and ceilings associated with the Whitney Young Community Building Project, increasing the amount by $31,219.37, raising the total Contract amount from $216,700.00 to $247,919.37. [Div. of Parks and Recreation, Conrad]
Summary
Authorization to execute Change Order #1 with Elaine Allen to increase the original bid price of the Whitney Young Community Building project due to the additional work needed to replace a failed septic system and make modifications to walls and ceilings. The increased amount is $31,219.37, bringing the new Contract total to $247,919.37. Funds are Budgeted. (L0313-26)(Conrad/Ford)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: No
Risk Management: No
Fully Budgeted [select]: Yes
Account Number: 1148-707602-7221-91012
This Fiscal Year Impact: $31,219.37
Annual Impact: No
Project: GSPK_WHITNEY_YG
Activity: RENOVATE
Budget Reference: 2026
Current Balance: $ 83,186.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Elaine Allen, for replacement of a failed septic system and modifications to walls and ceilings associated with the Whitney Young Community Building Project, increasing the total amount by $31,219.37, raising the total Contract amount from $216,700.00 to $247,919.37.
Section 2 - That an amount, not to exceed the additional sum of $31,219.37, is hereby authorized for payment to Elaine Allen, from account # 1148-707602-91012, pursuant to the terms of Change Order No. 1.
Section 3 - That this Resolu...