header-left
File #: 0844-15    Version: 1 Name: Approval Change Order #1 - LAGCO
Type: Resolution Status: Approved
File created: 6/18/2015 In control: Urban County Council
On agenda: 7/7/2015 Final action: 7/7/2015
Enactment date: 7/7/2015 Enactment #: R-456-2015
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Contract with Lagco, Inc., for the Plumbing/Water Softener Projects at the Div. of Community Corrections, increasing the contract price by the sum of $2,476.50 from $278,900.00 to $281,376.50. [Div. of Community Corrections, Ballard]
Attachments: 1. Memo Approving Change Request 1_LAGCO, 2. LAGCO Change Order Form, 3. LAGCO_CHANGE ORDER, 4. R-456-2015, 5. contract 29-2015
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Contract with Lagco, Inc., for the Plumbing/Water Softener Projects at the Div. of Community Corrections, increasing the contract price by the sum of $2,476.50 from $278,900.00 to $281,376.50. [Div. of Community Corrections, Ballard]
Summary
Authorization to execute a change order to the original agreement with LAGCO, Inc. approved with R61-2015 for the plumbing/water softener projects at the Division of Community Corrections. The change order is to install two tees for the flow switches on the hot water heater. The change order request is for $2,476.50. The original contract was for $278,900. The change order request brings the total cost of the project to $281,376.50. Funds are budgeted. (L0844-15)(Ballard/Bastin)

Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Select Yes/No, Completed by [Attorney Name, Date]}
Risk Management: {Select Yes/No, Completed by [Official, Date]}
Fully Budgeted [select]: Yes
Account Number: 1105-505401-5412-90511
This Fiscal Year Impact: $2,476.50
Annual Impact: $
Project: DET_WTRSOFT_2014
Activity: COUNCIL
Budget Reference: 2014
Current Balance: $15,100
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the contract with LAGCO, Inc., for the Plumbing/Water Softener Projects at the Division of Community Corrections, increasing the contract price by the sum of $2,476.50 from $278,900.00 to $281,376.50.
Section 2 - That an amount, not to exceed the sum of $2,476.50, be and hereby is approved for payment to LAGCO, Inc., from account #1105-505401-5412-90511 pursuant to the terms of the Change Order.
Section 3 - That this R...