File #: 1236-18    Version: 1 Name: Main Street Baptist Parking
Type: Resolution Status: Approved
File created: 11/12/2018 In control: Urban County Council
On agenda: 12/4/2018 Final action: 12/4/2018
Enactment date: 12/4/2018 Enactment #: R-736-2018
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute a Memorandum of Understanding (MOU) with Main Street Baptist Church, for short-term, temporary parking during the construction of the Lexington Civic Center (LCC) Expansion Project, on a portion of the right-of-way located on Jefferson St. in downtown Lexington, beginning upon the completed construction of a temporary surface parking lot and continuing for a term of three (3) years with two (2) automatic renewals of one (1) year each unless terminated by either party, at a cost not to exceed $90,000, subject to the sufficient appropriation of funds. [Mayor's Office, Peacher]
Attachments: 1. MOU_MSB_interimparking 11.2018.pdf, 2. BSMemo_MOU MSB_interimparking 11.13.2018.pdf, 3. 00634914.pdf, 4. R-736-2018, 5. C-289-2018
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute a Memorandum of Understanding (MOU) with Main Street Baptist Church, for short-term, temporary parking during the construction of the Lexington Civic Center (LCC) Expansion Project, on a portion of the right-of-way located on Jefferson St. in downtown Lexington, beginning upon the completed construction of a temporary surface parking lot and continuing for a term of three (3) years with two (2) automatic renewals of one (1) year each unless terminated by either party, at a cost not to exceed $90,000, subject to the sufficient appropriation of funds. [Mayor's Office, Peacher]
Summary
Authorization to execute a Memorandum of Agreement with Main Street Baptist Church to provide short-term temporary parking at no cost to Main Street Baptist Church during this construction of the Lexington Civic Center. The cost for this Fiscal Year is $90,000. Budget Amendment is in process. (L1236-18) (Peacher/Reed)
Budgetary Implications:
Advance Document Review:
Law: { Select Yes/No, Completed by [Attorney Name, Date]}
Risk Management: {Select Yes/No, Completed by [Official, Date]}
Fully Budgeted: BA 9686 in process
Account Number: 1105-133002-0001-90111
This Fiscal Year Impact: $90,000
Annual Impact: $
Project: JEFF_PKING_2019
Activity: CONSTRUCT
Budget Reference: 2019
Current Balance: BA 9686 in process
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute the Memorandum of Understanding (MOU), which is attached hereto and incorporated herein by reference, with Main Street Baptist Church, for short-term, temporary parking during the construction of the Lexington Civic Center Expansion Project, on a portion of the right-of-way located on Jefferson Street in downtown Lexington, beginning upon the...