Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Contract with Bush & Burchett, Inc., for the Grimes Mill Rd. Bridge Replacement at Boone's Creek, for the Div. of Grants and Special Programs, increasing the contract price by the sum of $50,676.00 from $643,172.59 to $693,848.59. [Div. of Grants and Special Programs/Dept. of Planning, Preservation and Development, Gooding/Paulsen]
Summary
Authorization to execute Change Order No. 1 to Construction Contract with Bush & Burchett, Inc., for the reconstruction of Grimes Mill Road Bridge Replacement at Boone's Creek Project. (L0199-14) (Gooding/Paulsen)
This is a request to execute Change Order No. 1 to Construction Contract with Bush & Burchett, Inc., for an amount of $50,676 for the reconstruction of Grimes Mill Road Bridge Replacement at Boone's Creek Project. This increase brings the new contract total amount to $693,848.59. Funds are budgeted.
Budgetary Implications: YES
Advance Document Review: Law/Risk Management
Fully Budgeted: YES
Account Number: 3160-303201-0001-91712; 1137-303301-0001-91712
This Fiscal Year Impact: $44,557.31; $6,118.69
Annual Impact: $50,676
Project: GRIMES_ML_2006
Activity: FED_GRANT
Budget Reference: 2006
Current Balance: encumbered
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. One (1), which is attached hereto and incorporated herein by reference, to the Contract with Bush & Burchett, Inc., for the Grimes Mill Road Bridge Replacement at Boone's Creek, for the Division of Grants and Special Programs, increasing the contract price by the sum of $50,676.00 from $643,172.59 to $693,848.59.
Section 2 - That an amount, not to exceed the sum of $50,676.00, be and hereby is approved for payment to Bush & Bur...