header-left
File #: 0283-16    Version: 1 Name: Alpha Mechanical CO#2-713-2015
Type: Resolution Status: Approved
File created: 3/14/2016 In control: Urban County Council
On agenda: 4/21/2016 Final action: 4/21/2016
Enactment date: 4/21/2016 Enactment #: R-205-2016
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Alpha Mechanical Services, Inc. for the Government Center Boiler Replacement Project, increasing the contract price by the sum of $3,100 from $79,267 to $82,367. [Div. of Facilities and Fleet Management, Baradaran]
Attachments: 1. Authorization Letter CO#2 Alpha Mech, 2. Change Order #2 Alpha.PDF, 3. Justification CO#2 Alpha Mech GC Boilers.PDF, 4. Alpha Mechanical CO#2 proposal.PDF, 5. 0283-16, 6. 00528676.pdf, 7. RESOLUTION - 205-2016.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Alpha Mechanical Services, Inc. for the Government Center Boiler Replacement Project, increasing the contract price by the sum of $3,100 from $79,267 to $82,367. [Div. of Facilities and Fleet Management, Baradaran]
Summary
Authorization to Execute Change Order #2 with Alpha Mechanical Services, Inc for the increase amount of $3,100.00 to provide (2) gas pressure regulators with over pressure device for the new boilers at the Government Center per contract # 713-2015. The new contract amount including this Change Order is $82,367.00. (L0283-16) (Baradaran/Reed).
Budgetary Implications [select]: Yes
Advance Document Review:
Law: NA
Risk Management: NA
Fully Budgeted: Yes
Account Number: 2606-707201-0001-91012
This Fiscal Year Impact: $3,100.00
Annual Impact: $
Project: BLD_REPAIR_2016
Activity: REPAIRMAIN
Budget Reference: 2016
Current Balance: $645,000.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the contract with Alpha Mechanical Services, Inc. for the Government Center Boiler Replacement Project, increasing the contract price by the sum of $3,100.00 from $79,267.00 to $82,367.00.
Section 2 - That an amount, not to exceed the sum of $3,100.00, be and hereby is approved for payment to Alpha Mechanical Services, Inc. from account #2606-707201-0001-91012 pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:





___________________________________
MAYOR

ATTEST:

________________________________
CLERK OF URBAN COUNTY COUNCIL
...

Click here for full text