File #: 0986-22    Version: 1 Name: Change Order #3 (Final) Peachtree Stormwater Improv.
Type: Resolution Status: Approved
File created: 9/26/2022 In control: Urban County Council
On agenda: 10/27/2022 Final action: 10/27/2022
Enactment date: 10/27/2022 Enactment #: R-577-2022
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three (3) (Final) to the Agreement with MAC Construction & Excavating, Inc., for the Peachtree Rd.-Woodhill Drive Stormwater Improvements, increasing the Contract price by $262,533.63, and raising the total Contract price from $2,935,204.34 to $3,197,737.97. [Div. of Water Quality, Martin]
Attachments: 1. BlueSheet Memo Change Order#3, 2. Change Order Contract, 3. Change Order Map, 4. Change Order Modification, 5. 00766478.pdf, 6. R-577-2022
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three (3) (Final) to the Agreement with MAC Construction & Excavating, Inc., for the Peachtree Rd.-Woodhill Drive Stormwater Improvements, increasing the Contract price by $262,533.63, and raising the total Contract price from $2,935,204.34 to $3,197,737.97. [Div. of Water Quality, Martin]
Summary
Authorization to approve Change Order No. 3 (final) with MAC Construction & Excavating Inc. for additional trenching, curb and gutter work, and traffic control for the Peachtree Road & Woodhill Drive Stormwater Improvements Project, increasing the Contract price by $262,533.63 for a total Contract price of $3,197,737,97. Funds are Budgeted. (L0986-22)(Martin/Albright)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: Yes, Completed by Evan P. Thompson 9/23/2022
Risk Management: No
Fully Budgeted [se,lect]: Yes
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $262,533.63
Annual Impact: $
Project: PEACHTREE_WOOD
Activity: CONSTRUCT
Budget Reference: 2019
Current Balance: $452,851.03
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
Three (3) (FINAL) which is attached hereto and incorporated herein by reference, to the Agreement with MAC Construction & Excavating, Inc., for the Peachtree Road-Woodhill Drive Stormwater Improvements, increasing the Contract price by $262,533.63, and raising the total Contract price from $2,935,204.34 to $3,197,737.97.
Section 2 - That an amount, not to exceed the sum of $262,533.63, is hereby authorized for payment to MAC Construction & Excavating, Inc., from account # 4052-303204-92211, pursuant to the terms of Change Order No. Three (3) (FINAL).
Section 3 - That this Resolution shall...