Legislation Details

File #: 0663-26    Version: 2 Name: Request Council authorization to execute Change Order No. 3 between the Lexington-Fayette Urban County Government (LFUCG) and GRW Engineers, Inc. to provide additional design services for the Town Branch WWTP Dewatering Pump Station Improvements. Change O
Type: Resolution Status: Second Reading
File created: 8/3/2026 In control: Urban County Council
On agenda: 8/27/2026 Final action:
Enactment date: Enactment #:
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Agreement with GRW Engineers, Inc., for design services for Town Branch WWTP Dewatering Pump Station Improvements, for the Div. of Grants and Special Programs, increasing the Contract by the sum of $6,462.19, from $402,644.00 to $409,106.19. [Div. of Water Quality, Sanders]
Attachments: 1. 27-Blue Sheet CO No. 3 GRW Engineers Inc, 2. Contract Change Order, 3. RESO 0663-26 Change Order No.3 TB Dewatering Improvements 4925-2233-6709 v.1.pdf
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Agreement with GRW Engineers, Inc., for design services for Town Branch WWTP Dewatering Pump Station Improvements, for the Div. of Grants and Special Programs, increasing the Contract by the sum of $6,462.19, from $402,644.00 to $409,106.19. [Div. of Water Quality, Sanders]
Summary
Authorization to execute Change Order No. 3 with GRW Engineers, Inc. to provide additional design services for the Town Branch WWTP Dewatering Pump Station Improvements (Contract #661-2023). Change Order No. 3 is for $6,462.19 and will increase the Contract to $409,106.19. Funds are Budgeted. (L0663-26)(Sanders/Martin)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Todd Henning, 7/31/2026
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 3230-303401-3401-92711
This Fiscal Year Impact: $6,462.19
Annual Impact: $0
Project: TBWWTP_2023
Activity: FED_GRANT
Budget Reference: 2023
Current Balance: $763,329.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 3, which is attached hereto and incorporated herein by reference, to the Agreement with GRW Engineers, Inc., for Design Services for Town Branch WWTP Dewatering Pump Station Improvements, for the Division Of Grants And Special Programs, increasing the Contract price by the sum of $6,462.19, from $402,644.00 to $409,106.19.
Section 2 - That an amount, not to exceed the sum of $6,462.19, be and hereby is approved for payment to GRW Engineers, Inc., from account # 3230-303401-92711, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:


________________________________
MAYO...

Click here for full text