File #: 0796-20    Version: 1 Name: Change Order No. 6 Southland Area Stormwater Improvement Project Banks Engineering
Type: Resolution Status: Approved
File created: 8/17/2020 In control: Urban County Council
On agenda: 9/3/2020 Final action: 9/3/2020
Enactment date: 9/3/2020 Enactment #: R-413-2020
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 6 to the Agreement with Banks Engineering, Inc., for the Southland Area Stormwater Improvement Project, increasing the Contract Price by the sum of $20,000, from $654,815 to $674,815. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. Supporting Documents, 4. Map, 5. 00692871.pdf, 6. R-413-2020, 7. Contract #035-2017

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 6 to the Agreement with Banks Engineering, Inc., for the Southland Area Stormwater Improvement Project, increasing the Contract Price by the sum of $20,000, from $654,815 to $674,815. [Div. of Water Quality, Martin]

Summary

Authorization to execute Change Order No. 6 to the Agreement with Banks Engineering, Inc., for the Southland Area Stormwater Improvement Project, increasing the Contract price by the sum of $20,000.00, from $654,815.00 to $674,815.00. Funds are Budgeted. (L0796-20) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 8/14/20]}

Risk Management:  {no}

Fully Budgeted [select]: Yes

Account Number:                     4052-303204-3334-92211

This Fiscal Year Impact:                     $20,000.00

Annual Impact:                      $

Project: WR_SOUTHLAND

Activity: CONSENT_DE

Budget Reference: 2019

Current Balance: $1,399,958.61

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 6, which is attached hereto and incorporated herein by reference, to the Agreement with Banks Engineering, Inc., for the Southland Area Stormwater Improvement Project, increasing the Contract price by the sum of $20,000.00, from $654,815.00 to $674,815.00.

                     Section 2 - That an amount, not to exceed the sum of $20,000.00, be and hereby is approved for payment to Banks Engineering, Inc., from account # 4052 -  303204 - 92211, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.