File #: 0728-16    Version: 1 Name: Rogers Rd Stormwater Improvement Project
Type: Resolution Status: Approved
File created: 6/13/2016 In control: Urban County Council
On agenda: 7/5/2016 Final action: 7/5/2016
Enactment date: 7/5/2016 Enactment #: R-440-2016
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Bluegrass Contracting Corporation for the Rogers Rd. Stormwater Improvements Project, increasing the contract price by the sum of $13,935.90 from $2,838,990.22 to $2,852,926.12, and extending the date of completion by seven (7) calendar days, to November 4, 2016. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. Change Order History Forms, 3. Change Order Amounts, 4. Map of Area, 5. 00539103.pdf, 6. RESOLUTION - 440-2016.pdf, 7. 291-2015 CONTRACT.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Bluegrass Contracting Corporation for the Rogers Rd. Stormwater Improvements Project, increasing the contract price by the sum of $13,935.90 from $2,838,990.22 to $2,852,926.12, and extending the date of completion by seven (7) calendar days, to November 4, 2016. [Div. of Water Quality, Martin]
Summary
Authorization to approve Change Order #1 to the LFUCG Contract with Bluegrass Contracting for construction services associated with the Rogers Road Stormwater project. The purpose of this request is to compensate the Contractor for expenses related to the relocation of an existing sanitary manhole that was not shown on the plans and to extend the project completion date by seven (7) calendar days. The new project completion date is November 4, 2016. The Change Order request is $13,935.90 which is a 0.5% increase to the Contract amount. Funds are Budgeted. (L0728-16) (Martin/Hoskins-Squier)
Budgetary Implications: Yes
Advance Document Review:
Law: No
Risk Management: No
Fully Budgeted: Yes
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $13,935.90
Annual Impact: $
Project: ROGERS_2013
Activity: CONSTRUCT
Budget Reference: 2013
Current Balance: $228,170.22
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Bluegrass Contracting Corporation for the Rogers Road Stormwater Improvements Project, increasing the Contract price by the sum of $13,935.90 from $2,838,990.22 to $2,852,926.12 and extending the date of completion by seven (7) calendar days, to November 4, 2016.
Section 2 - That an amount, not to exceed the sum of $13,935.90...