Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Contract with E.C. Matthews, for the Woodland Park Restroom Building, decreasing the contract price by the sum of $3,075, from $527,550 to $524,475. [Div. of Parks and Recreation, Conrad]
Summary
Authorization to execute Change Order No. 3 to the Agreement with E.C. Matthews for the Woodland Restroom Building, a LFUCG approved American Rescue Plan Act project, reducing the Contract price by $3,075.00. The new Contract total is $524,475.00. (L0777-22) (Conrad/Ford)
Budgetary Implications: Yes
Advance Document Review:
Law: No
Risk Management: No
Fully Budgeted: Yes
Account Number: 3230 707602 7221 90511
This Fiscal Year Impact: ($3,075.00)
Annual Impact: N/A
Project: AR_WDLAND_2022
Activity: FED_GRANT
Budget Reference: 2022
Current Balance: $2,271.40
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. , which is attached hereto and incorporated herein by reference, to the Contract with E.C. Matthews Co. Inc., for the Woodland Park Restroom Building, decreasing the contract price by the sum of $3,075.00, from $527,550.00 to $524,475.00.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
_
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL
0777-22:CEC:X:\Cases\PARKS\22-LE0003\LEG\00762850.DOCX