File #: 0034-21    Version: 2 Name: Request Council authorization to execute Change Order No.1 with Pace Contracting for the Town Branch Commons Corridor Construction Project for work in Zone 2, increasing the contract price by the sum of $161,290.82 from $20,193,934.98 to $20,355,225.80.
Type: Resolution Status: Approved
File created: 1/4/2021 In control: Urban County Council
On agenda: 1/28/2021 Final action: 1/28/2021
Enactment date: 1/28/2021 Enactment #: R-041-2021
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Agreement with Pace Contracting, LLC, for the Town Branch Commons Corridor Construction Project, Zone 2, increasing the Contract price by the sum of $161,290.82, changing the total Contract price from $20,193,934.98 to $20,355,225.80. [Mayor's Office, Peacher]
Attachments: 1. 21-blue sheet memo PACE Change Order #1, 2. Pace Change Order No. 1, 3. TBC_CO1-Approved KYTC reduced file, 4. 00717254.pdf, 5. R-041-2021

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Agreement with Pace Contracting, LLC, for the Town Branch Commons Corridor Construction Project, Zone 2, increasing the Contract price by the sum of $161,290.82, changing the total Contract price from $20,193,934.98 to $20,355,225.80. [Mayor's Office, Peacher]

 

Summary

Authorization to execute Change Order No.1 with Pace Contracting for the Town Branch Commons Corridor Construction Project for work in Zone 2, increasing the Contract price by the sum of $161,290.82 from $20,193,934.98 to $20,355,225.80. Funds are Budgeted. (L0034-21) (Peacher/Scott)

Budgetary Implications: Yes

Advance Document Review:

Law: Yes, Completed by Brittany Smith, 12/15/2020

Risk Management:  N/A

Fully Budgeted: Yes

Account Number:                     3160-303202-3225-91715

This Fiscal Year Impact:                     $161,290.82

Annual Impact:                      $0

Project: TOWN_LEX_2016

Activity: CONSTRUCT

Budget Reference: 2016

Current Balance: $531,811.86

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. One (1), which is attached hereto and incorporated herein by reference, to the Agreement with Pace Contracting, LLC, for the Town Branch Commons Corridor Construction Project, Zone 2, increasing the contract price by the sum of $161,290.82, and changing the total contract price from $20,193,934.98 to $20,355,225.80.

                     Section 2 - That an amount, not to exceed the sum of $161,290.82, be and hereby is approved for payment to Pace Contracting, LLC, from account #3160-303202-91715, pursuant to the terms of the Change Order No. One (1).

                     Section 3 --That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL: