Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (final) to the Agreement with Herrick Co., Inc., for the Hartland Pump Station No. 3 Replacement Project, decreasing the Contract price by $149,904.76, from $1,110,000.00 to $960,095.24. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No.1 (final) to the Agreement with Herrick Company Inc. for the Hartland 3 Pump Station Replacement project, decreasing the Contract price by the sum of $149,904.76 from $1,110,000.00 to $960,095.24. The decrease is due to the deletion of bid items not necessary for the project’s completion. (L1091-23) (Martin/Albright)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: Yes, Completed by Evan P. Thompson 10/18/2023
Risk Management: No
Fully Budgeted [select]: N/A
Account Number: 4003-303408-3466-92811
This Fiscal Year Impact: -$149,904.76
Annual Impact: $
Project: HARTLANDPS_RMP
Activity: CONSENT_DE
Budget Reference:
Current Balance: $688,592.52
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
1 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with Herrick Company, Inc., for the Hartland Pump Station No. 3 Replacement Project, decreasing the contract price by $149,904.76, from $1,110,000.00 to $960,095.24.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
______________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL