A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 4 to the Agreement with Palmer Engineering, for the Town Branch Trail Phase 5 Project, increasing the Contract price by the sum of $23,000, from $786,002 to $809,002. [Div. of Engineering, Burton]
Summary
Authorization to execute Contract Modification No. 4 with Palmer Engineering for design revisions on Town Branch Trail Phase 5 project for Division of Waste Management and Republic Services to retain access to the transfer station alternative entrance, and to tie-in a storm sewer from the separate Town Branch Trail Crossing project designed by others. Increasing the Contract amount by $23,000 from $786,002 to $809,002. Funds are Budgeted. (L0413-25)(Burton/Albright)
Budgetary Implications: Yes
Advance Document Review:
Law: Yes, Completed by Mike Sanner, 4/18/2025
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 3160-303202-3225-90313
This Fiscal Year Impact: $23,000.00
Annual Impact: $0
Project: TOWNBRNC_2015
Activity: VI_DES_A
Budget Reference: 2015
Current Balance: $60,450.06
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 4, which is attached hereto and incorporated herein by reference, to the Agreement with Palmer Engineering, for the Town Branch Trail Phase 5 Project, increasing the Contract price by the sum of $23,000.00, from $786,002.00 to $809,002.00.
Section 2 - That an amount, not to exceed the sum of $23,000.00, be and hereby is approved for payment to Palmer Engineering, from account #3160-303202-90313.
Section 3 - That this Resolution shall become effective on the date of its passage.