header-left
File #: 00390-11    Version: 1 Name: Woodall Construction -Change #3
Type: Resolution Status: Approved
File created: 11/7/2011 In control: Urban County Council
On agenda: 12/1/2011 Final action: 12/1/2011
Enactment date: 12/1/2011 Enactment #: R-539-2011
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three to the Contract with Woodall Construction Co., Inc., for the Lexington Streetscape Phase One Improvements, E. Main St. Streetscape Project, increasing the contract price by the sum of $55,938.35 from $2,707,143.50 to $2,763,081.85.
Attachments: 1. Woodall Construction Change Order 3 memo.pdf, 2. Woodall Construction-CHANGE 3.pdf

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three to the Contract with Woodall Construction Co., Inc., for the Lexington Streetscape Phase One Improvements, E. Main St. Streetscape Project, increasing the contract price by the sum of $55,938.35 from $2,707,143.50 to $2,763,081.85. 

Summary

Request Council authorization to execute Change Order No. 3 to Contract 086-2010 with Woodall Construction in the amount of $55,938.35 for the Lexington Streetscape Phase One Improvements, East Main Street Streetscape Project.

 

The Division of Environmental Quality and Public Works is recommending the execution of change order No. 3 for $55,938.35 with Woodall Construction for the construction of the Lexington Streetscape Phase One Improvements, East Main Streetscape Project. The new contract total is $2,763,081.85.

 

The change order adds units that were not included in the original contract but were needed for the replacement of 112’ of 12” sanitary sewer main at 200 E. Main The elimination of 2 existing manholes, adding 1 new manhole and modifying 1 existing manhole. This item was shown on the original plans but units could not be determined until after exploration of existing facilities was completed

Budgetary Implications: Yes

Advance Document Review: Law/Risk Management

Fully Budgeted: Yes

Account Number:                     4003-303408-3462-92811

This Fiscal Year Impact:                     $ 55,938.35

Annual Impact:                      $

Project: SSREHAB_2012

Activity: Construct

Budget Reference: 2012

Current Balance: $1,247,600