Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three to the Contract with Woodall Construction Co., Inc., for the Lexington Streetscape Phase One Improvements, E. Main St. Streetscape Project, increasing the contract price by the sum of $55,938.35 from $2,707,143.50 to $2,763,081.85.
Summary
Request Council authorization to execute Change Order No. 3 to Contract 086-2010 with Woodall Construction in the amount of $55,938.35 for the Lexington Streetscape Phase One Improvements, East Main Street Streetscape Project.
The Division of Environmental Quality and Public Works is recommending the execution of change order No. 3 for $55,938.35 with Woodall Construction for the construction of the Lexington Streetscape Phase One Improvements, East Main Streetscape Project. The new contract total is $2,763,081.85.
The change order adds units that were not included in the original contract but were needed for the replacement of 112’ of 12” sanitary sewer main at 200 E. Main The elimination of 2 existing manholes, adding 1 new manhole and modifying 1 existing manhole. This item was shown on the original plans but units could not be determined until after exploration of existing facilities was completed
Budgetary Implications: Yes
Advance Document Review: Law/Risk Management
Fully Budgeted: Yes
Account Number: 4003-303408-3462-92811
This Fiscal Year Impact: $ 55,938.35
Annual Impact: $
Project: SSREHAB_2012
Activity: Construct
Budget Reference: 2012
Current Balance: $1,247,600