File #: 1224-19    Version: 1 Name: Change Order No. 1 (Final) Firethorn Detention Basin
Type: Resolution Status: Approved
File created: 11/8/2019 In control: Urban County Council
On agenda: 12/3/2019 Final action: 12/3/2019
Enactment date: 12/3/2019 Enactment #: R-681-2019
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Agreement with Trademark Excavating Co., LLC, for the Firethorn Detention Basin Water Quality Improvements Project, decreasing the contract price by the sum of $22,000, from $115,000 to $93,000. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. Map, 4. 00672353.pdf, 5. RESOLUTION #681-2019, 6. Contract #149-2019

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Agreement with Trademark Excavating Co., LLC, for the Firethorn Detention Basin Water Quality Improvements Project, decreasing the contract price by the sum of $22,000, from $115,000 to $93,000. [Div. of Water Quality, Martin]

 

Summary

Authorization to execute Change Order No. 1 (Final) to the Agreement with Trademark Excavating Company, LLC, for the Firethorn Detention Basin Water Quality Improvements Project, decreasing the Contract price by the sum of $22,000.00, from $115,000.00 to $93,000.00. (L1224-19) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 11/8/19]}

Risk Management:  {No}

Fully Budgeted [select]: N/A

Account Number:                     

This Fiscal Year Impact:                      -$22,000

Annual Impact:                      $

Project:

Activity:

Budget Reference:

Current Balance:

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with Trademark Excavating Company, LLC, for the Firethorn Detention Basin Water Quality Improvements Project, decreasing the Contract price by the sum of $22,000.00, from $115,000.00 to $93,000.00.

                     Section 2 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

                                                                                                                                                                                                                                       

                                                                                                                              MAYOR

 

ATTEST:

 

_________________________________

CLERK OF URBAN COUNTY COUNCIL

1224-19_MSC_X:\Cases\WATER-AIR\19-LE0001\LEG\00672353.DOCX