header-left
File #: 0240-12    Version: Name: Griffin Gate #2 Pump Station - Changer Order #1 (Final)
Type: Resolution Status: Approved
File created: 2/27/2012 In control: Urban County Council
On agenda: 3/22/2012 Final action: 3/22/2012
Enactment date: 3/22/2012 Enactment #: R-127-2012
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) (Final) to the Contract with Grant’s Excavating, Inc. for the Griffin Gate Pump Station Replacement Project, increasing the contract price by the sum of $5,105 from $173,000 to $178,105. [Div. of Water Quality, Martin]
Attachments: 1. Griffin Gate #2 PS - Change Order - Memo.pdf, 2. Griffin Gate #2 PS - Change Order - Info Sheet.pdf, 3. Griffin Gate #2 PS - Change Order - Contract History.pdf, 4. Griffin Gate #2 PS - Change Order - Signature Sheet.pdf, 5. 00337209.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) (Final) to the Contract with Grant’s Excavating, Inc. for the Griffin Gate Pump Station Replacement Project, increasing the contract price by the sum of $5,105 from $173,000 to $178,105. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No. 1 (Final) with Grant’s Excavating Inc. for the Griffin Gate Pump Station Replacement project. (L240-12) (Martin/Moloney)
This is a request to execute Change Order No. 1 (Final) with Grant’s Excavating Inc. that will increase the sum of the contract by $5,105.00 for the Griffin Gate Pump Station Replacement project. This change order gives the revised total contract amount of $178,105.00. Funds are budgeted.

Budgetary Implications: Yes
Advance Document Review: Law/Risk Management
Fully Budgeted: Yes
Account Number: 4003-303406-3452-92811
This Fiscal Year Impact: $5105
Annual Impact: NA
Project: GRIFFINPS_2011
Activity: CONSTRUCT
Budget Reference: 2011
Current Balance: Pre-encumbered
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. One (1) (Final), which is attached hereto and incorporated herein by reference, to the Contract with Grant’s Excavating, Inc. for the Griffin Gate Pump Station Replacement project, increasing the contract price by the sum of $5,105.00 from $173,000.00 to $178,105.00.
Section 2 - That an amount, not to exceed the sum of $5,105.00, be and hereby is approved for payment to Grant’s Excavating, Inc., from account # 4003-303406-92811, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.