header-left
File #: 0057-22    Version: 1 Name: Change Order #1-Flottweg Centrifuge Rebuild-TB
Type: Resolution Status: Approved
File created: 1/10/2022 In control: Urban County Council
On agenda: 2/10/2022 Final action: 2/10/2022
Enactment date: 2/10/2022 Enactment #: R-044-2022
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Flottweg Separation Technology, Inc., for the Town Branch Waste Water Treatment Plant Centrifuge Rebuild Project, increasing the Contract price by the sum of $24,000, from $100,000 to $124,000. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. Change Order Forms, 3. Estimate, 4. Additional Information, 5. 00747001.pdf, 6. R-044-2022, 7. Contract #259-2020, 8. C-002-2022

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Flottweg Separation Technology, Inc., for the Town Branch Waste Water Treatment Plant Centrifuge Rebuild Project, increasing the Contract price by the sum of $24,000, from $100,000 to $124,000. [Div. of Water Quality, Martin]

 

 

Summary

Authorization to execute Change Order No. 1 to the Agreement with Flottweg Separation Technology, Inc., for the Town Branch Waste Water Treatment Plant Centrifuge Rebuild Project, increasing the cost of procurement by the sum of $24,000.00, from $100,000 to $124,000. Funds are Budgeted. (L0057-22) (Martin/Albright)

Budgetary Implications: Yes

Advance Document Review:

Law: Yes, Completed by Michael Cravens, 1/10/2022

Risk Management:  No

Fully Budgeted: Yes

Account Number: 4002 303402 0001 76101                     

This Fiscal Year Impact:                     $24,000.00

Annual Impact:                      $

Project:

Activity:

Budget Reference: 2022

Current Balance: $179,780.71

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Flottweg Separation Technology, Inc., for the Town Branch Waste Water Treatment Plant Centrifuge Rebuild Project, increasing the contract price by the sum of $24,000.00, from $100,000.00 to $124,000.00.

                     Section 2 - That an amount, not to exceed the sum of $24,000.00, be and hereby is approved for payment to Flottweg Separation Technology, Inc., from account # 4002 - 303402 - 76101, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                                                                                             __                     _                     

                                                                                                                              MAYOR