Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute an Agreement with Garland / DBS, Inc., for construction services for the Waste Management Facility Roof Restoration Project, at a cost not to exceed $274,986. [Div. of Facilities and Fleet Management, Baradaran]
Summary
Authorization to execute a Construction Services Agreement with Garland / DBS, Inc. for the Waste Management Facility Roof Restoration Project in the amount of $274,986. Funds are Budgeted. (L0543-22) (Baradaran/Ford)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: N/A
Risk Management: N/A
Fully Budgeted: Yes
Account Number: 1115-707201-0001-91012
This Fiscal Year Impact: $274,986
Annual Impact: N/A
Project:
Activity:
Budget Reference:
Current Balance: $283,800.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute the Agreement with Garland / DBS, Inc., which is attached hereto and incorporated by reference, for construction services for the Waste Management Facility Roof Restoration Project, at a cost not to exceed $274,986.00.
Section 2 - That an amount, not to exceed the sum of $274,986.00, be and hereby is approved for payment to Garland / DBS, Inc., from account # 1115-707201-0001-91012, pursuant to the terms of the Agreement.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: