File #: 0725-25    Version: 1 Name: Change Order #3 - BMI Builds - #116-2024
Type: Resolution Status: First Reading
File created: 8/4/2025 In control: Urban County Council
On agenda: 8/14/2025 Final action:
Enactment date: Enactment #:
Title: Authorization to execute Change Order #3 with BMI Builds LLC for the Valley Park Building Renovation & Expansion in the amount of $198,320.00 increasing the contract from $1,795,001.26 to $1,993,321.26 to integrate the Parks Site Masterplan, resulting in a sixty-one (61) calendar day change to the contract time. Funds are budgeted. (L0725-25)(Ford)
Attachments: 1. Memo-BMI Builds -CO3, 2. Change Order Contract Details Form_CO3, 3. Justification for CO3_BMI Builds, 4. BMI_CO3_Proposal Request, 5. BMI_CO3_Documentation for Change, 6. RESO 0725-25 4917-9812-9499 v.1.docx

Title

Authorization to execute Change Order #3 with BMI Builds LLC for the Valley Park Building Renovation & Expansion in the amount of $198,320.00 increasing the contract from $1,795,001.26 to $1,993,321.26 to integrate the Parks Site Masterplan, resulting in a sixty-one (61) calendar day change to the contract time. Funds are budgeted. (L0725-25)(Ford)

Summary

Authorization to execute Change Order #3 with BMI Builds LLC for the Valley Park Building Renovation & Expansion in the amount of $198,320.00 increasing the contract from $1,795,001.26 to $1,993,321.26 to integrate the Parks Site Masterplan, resulting in a sixty-one (61) calendar day change to the contract time. Funds are budgeted. (L0725-25)(Ford)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: N/A

Risk Management:  N/A

Fully Budgeted [select]: Yes

Account Number: 1105-707602-7221-91015-                     

This Fiscal Year Impact:                     $198,320.00

Annual Impact:                      $0

Project: VALLEY_PK_2024

Activity: COUNCIL

Budget Reference: 2024

Current Balance: $445,160.24