Title
Authorization to Execute Change Order #3 with Schaefer Contracting, LLC in the amount of $5,568.00 and an additional twenty-two (22) calendar days to the schedule for the Masterson Station Park Restroom Building Contract #151-2015. The new contract amount including this change order is $188,851.00. Connection of the sanitary sewer and water lines were not in this contract’s original scope of work, nor captured in the construction of the sanitary sewer utility services price contract work. The contractor shall run piping and install associated plumbing items, tap on to the sanitary sewer system and have the work inspected. An additional 22 calendar days added to the construction schedule is needed to complete this work. Funds are budgeted. (L1463-15)(Reed)
Summary
Authorization to Execute Change Order #3 with Schaefer Contracting, LLC in the amount of $5,568.00 and an additional twenty-two (22) calendar days to the schedule for the Masterson Station Park Restroom Building Contract #151-2015. The new contract amount including this change order is $188,851.00. Connection of the sanitary sewer and water lines were not in this contract’s original scope of work, nor captured in the construction of the sanitary sewer utility services price contract work. The contractor shall run piping and install associated plumbing items, tap on to the sanitary sewer system and have the work inspected. An additional 22 calendar days added to the construction schedule is needed to complete this work. Funds are budgeted. (L1463-15)(Reed)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: NA
Risk Management: NA
Fully Budgeted [select]: Yes
Account Number: 1105 707602 7221 90319
This Fiscal Year Impact: $5,568.00
Annual Impact: NA
Project: MASTERSON_2014
Activity: COUNCIL
Budget Reference: 2014
Current Balance: 13,925.06
Body