header-left
File #: 1461-15    Version: 1 Name: Change Order #28 - Marrillia - #227-2014
Type: Agenda Item Status: Held in Committee
File created: 11/16/2015 In control: General Services
On agenda: Final action: 12/8/2015
Enactment date: Enactment #:
Title: Authorization to execute change order No. 28 for $41,188.00 with Marrillia Design & Construction, Lexington, Kentucky for the Senior Citizen Center Construction project. The new contract total is $10,274,082.37. This change order will provide undercutting and soil remediation in the entry drive from Life Lane which connects to the entrance of the new Senior Center where unsuitable soils were discovered. This work is necessary to prevent premature failure of the paving in that area. Funds are budgeted. (L1461-15)(Baradaran/Reed)
Attachments: 1. Memorandum - Marrillia CO#28 - #227-2014.pdf, 2. Change Order #28 - Marrillia - #227-2014.pdf, 3. Justification for Change - Marrillia CO#28 - #227-2014.pdf, 4. Documentation for Change - Marrillia CO#28 - #227-2014.pdf

Title

Authorization to execute change order No. 28 for $41,188.00 with Marrillia Design & Construction, Lexington, Kentucky for the Senior Citizen Center Construction project.  The new contract total is $10,274,082.37. This change order will provide undercutting and soil remediation in the entry drive from Life Lane which connects to the entrance of the new Senior Center where unsuitable soils were discovered.  This work is necessary to prevent premature failure of the paving in that area. Funds are budgeted. (L1461-15)(Baradaran/Reed)

Summary

Authorization to execute change order No. 28 for $41,188.00 with Marrillia Design & Construction, Lexington, Kentucky for the Senior Citizen Center Construction project.  The new contract total is $10,274,082.37. This change order will provide undercutting and soil remediation in the entry drive from Life Lane which connects to the entrance of the new Senior Center where unsuitable soils were discovered.  This work is necessary to prevent premature failure of the paving in that area. Funds are budgeted. (L1461-15)(Baradaran/Reed)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: N/A

Risk Management: N/A

Fully Budgeted [select]: Yes

Account Number:                     2600 606101 6001 90511

This Fiscal Year Impact:                     $41,188.00

Annual Impact:                      N/A

Project: SR_CITZN2_2015

Activity: CONSTRUCT

Budget Reference: 2015

Current Balance: $ 609,675.05

Body

{COUNCIL CLERK’S OFFICE WILL COMPLETE - Body of resolution or ordinance}