header-left
File #: 0808-17    Version: 1 Name: Change Order #2 - Tri-State CO#2 - #054-2017
Type: Resolution Status: Approved
File created: 7/3/2017 In control: Urban County Council
On agenda: 7/11/2017 Final action: 7/11/2017
Enactment date: 7/11/2017 Enactment #: R-480-2017
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Tri-State Roofing and Sheet Metal Co., for the Black & Williams Center Roof Replacement and Repairs Project, increasing the contract price by the sum of $29,800 from $225,249 to $255,049 and adding 42 calendar days to the construction schedule. [Div. of Facilities and Fleet Management, Baradaran]
Attachments: 1. Memorandum - Tri-State CO#2 - #054-2017.pdf, 2. Change Order #2 - Tri-State CO#2 - #054-2017.pdf, 3. Justification for Change - Tri-State CO#2 - #054-2017.pdf, 4. Documentation for Change - Tri-State CO#2 - #054-2017.pdf, 5. 00579909.pdf, 6. RESOLUTION - 480-2017.pdf, 7. 054-2017 - CONTRACT.pdf

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Tri-State Roofing and Sheet Metal Co., for the Black & Williams Center Roof Replacement and Repairs Project, increasing the contract price by the sum of $29,800 from $225,249 to $255,049 and adding 42 calendar days to the construction schedule. [Div. of Facilities and Fleet Management, Baradaran]

Summary

Authorization to execute Change Order No. Two (2) to the Contract with Tri-State Roofing and Sheet Metal Co., for the Black & Williams Center Roof Replacement & Repairs Project, increasing the Contract price in the amount of $29,800.00 from $225,249.00 to $255,049.00 with a 42 calendar day extension to the construction schedule. Funds are Budgeted. (L0808-17) (Baradaran/Reed)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: N/A

Risk Management:  N/A

Fully Budgeted [select]: Yes

Account Number:                     2607-707201-0001-76101

This Fiscal Year Impact:                     $29,800.00

Annual Impact:                      N/A

Project: FACILITY_2017

Activity: BUILD_IMPR

Budget Reference: 2017

Current Balance: $2,249,753.95

Body

                     BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Contract with Tri-State Roofing and Sheet Metal Co., for the Black & Williams Center Roof Replacement and Repairs Project, increasing the Contract price by the sum of $29,800.00 from $225,249.00 to $255,049.00 and adding 42 calendar days to the construction schedule.

                     Section 2 - That an amount, not to exceed the sum $29,800.00, be and hereby is approved for payment to Tri-State Roofing and Sheet Metal Co., from account #2607-707201-0001-76101 pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.