File #: 00494-11    Version: 1 Name: Beverly Avenue Sewer Improvements Project--Change Order No. 1 with Schroeder Construction, Inc.
Type: Resolution Status: Approved
File created: 11/28/2011 In control: Grants and Special Programs
On agenda: 12/6/2011 Final action: 12/6/2011
Enactment date: 12/6/2011 Enactment #: R-598-2011
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (Final) to the Contract with Schroeder Construction, Inc., for the Beverly Ave. Sanitary Sewer Improvements Project increasing the contract price by the sum of $25,657.88 from $672,135.00 to $697,792.88. [Div. of Grants and Special Programs/Dept. of Environmental Quality and Public Works, Gooding/Bush]
Attachments: 1. 12-Bluesheet memo-Change Order No. 1-Beverly Ave..pdf, 2. 12-Change Order No. 1-Beverly Ave..pdf, 3. 12-Contract History Form--Beverly Ave.-CO #1.pdf, 4. 12-Requisition for Change Order No. 1.pdf

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (Final) to the Contract with Schroeder Construction, Inc., for the Beverly Ave. Sanitary Sewer Improvements Project increasing the contract price by the sum of $25,657.88 from $672,135.00 to $697,792.88.  [Div. of Grants and Special Programs/Dept. of Environmental Quality and Public Works, Gooding/Bush]

 

Summary

Authorization to execute Change Order No. 1 (Final) with Schroeder Construction, Inc., for the Beverly Avenue Sanitary Sewer Improvements Project.   (L494-11) (Gooding/Bush)

This is a request to execute Change Order No. 1 (Final) with Schroeder Construction, Inc., that will increase the sum of the contract by $25,657.88 for the completion of the Beverly Avenue Sanitary Sewer Improvements Project. This change order gives the revised total contract amount of $697,792.88. Funds are budgeted.

 

Budgetary Implications: Yes

Advance Document Review: Law/Risk Management

Fully Budgeted: Yes

Account Number:                     3400-303401-3401-92811

This Fiscal Year Impact:                     $25,657.88

Annual Impact:                      $

Project: UNSEWER2_2007

Activity: STA_GRANT

Budget Reference:  2007

Current Balance: $201,524.30

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. One (Final), which is attached hereto and incorporated herein by reference, to the Contract with Schroeder Construction, Inc., for the Beverly Avenue Sanitary Sewer Improvements Project increasing the contract price by the sum of $25,657.88 from $672,135.00 to $697,792.88.

                     Section 2 - That an amount, not to exceed the sum of $25,657.88, be and hereby is approved for payment to Schroeder Construction, Inc., from account #3400-303401-92811, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

 

 