File #: 1064-24    Version: Name: Change Order #1 Meadowthorpe SW Project
Type: Resolution Status: Second Reading
File created: 10/16/2024 In control: Urban County Council
On agenda: 11/21/2024 Final action:
Enactment date: Enactment #:
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Contract Agreement with Lagco, Inc, for the completion of Meadowthorpe Area Stormwater Improvement Project - Phase 1, increasing the Contract by the sum of $96,727.62, from $564,239.00 to $660,966.62. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. CO#1Meadowthorpe WQ, 3. Vicinity Map, 4. RESO 1064-24 Lagco Change Order 1 4874-5604-4534 v.1.pdf

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Contract Agreement with Lagco, Inc, for the completion of Meadowthorpe Area Stormwater Improvement Project - Phase 1, increasing the Contract by the sum of $96,727.62, from $564,239.00 to $660,966.62. [Div. of Water Quality, Martin]

 

Summary

Authorization to approve Change Order #1 (Final) with Lagco Inc. for completion of Meadowthorpe Area Stormwater Improvement Project - Phase 1 increasing the project cost by $96,727.62 to total $660,996.62. Funds are Budgeted. (L1064-24) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: Yes   Evan Thompson  10/7/24

Risk Management: No

Fully Budgeted [select]: Yes

Account Number:                     4052-303204-3334-92211

This Fiscal Year Impact:                     $96,727.62

Annual Impact:                      $

Project:  HILLSBORO

Activity: CONSTRUCT_CAP

Budget Reference: 2024

Current Balance: $912,537.00

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 1 (Final), which is attached hereto and incorporated herein by reference, to the Contract Agreement with Lagco, Inc., for completion of Meadowthorpe Area Stormwater Improvement Project - Phase 1, for the Division of Water Quality, increasing the contract price by the sum of $96,727.62, from $564,239.00 to $660,966.62.

                     Section 2 - That an amount, not to exceed the sum of $96,727.62, be and hereby is approved for payment to Lagco, Inc., from account # 4052-303204-3334-92211, pursuant to the terms of the Change Order.

Section 3 - That this Resolution shall become effective on the date of its passage.

PASSED URBAN COUNTY COUNCIL:


________________________________

MAYOR

 

ATTEST:

 

______________________________________

CLERK OF URBAN COUNTY COUNCIL

1064-24:EPT_4874-5604-4534, v. 1