File #: 0813-23    Version: 1 Name: Change Order No. 3 with Lagco, Inc. in the amount of $83,070.56 for construction of Meadows/Northland/Arlington Public Improvements Project, Phase 6B1 & 6B2.
Type: Resolution Status: Approved
File created: 8/11/2023 In control: Urban County Council
On agenda: 9/14/2023 Final action: 9/14/2023
Enactment date: 9/14/2023 Enactment #: R-474-2023
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Agreement with Lagco, Inc. for construction of the Meadows/Northland/Arlington Public Improvements Project, Phase 6B1 and 6B2, increasing the Contract price by $83,070.56, raising the total price to $2,855,950.20. [Div. of Engineering, Burton]
Attachments: 1. Bluesheet Memo for Change Order No. 3 with Lagco, Inc. for MNA Phase 6B1 & 6B2, 2. Contract Change Order and Justification, 3. Contract History Form, 4. Map of MNA Phase 6, 5. 00789674.pdf, 6. R-474-2023, 7. Contract #143-2021
Related files: 0627-21, 0271-22

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 to the Agreement with Lagco, Inc. for construction of the Meadows/Northland/Arlington Public Improvements Project, Phase 6B1 and 6B2, increasing the Contract price by $83,070.56, raising the total price to $2,855,950.20. [Div. of Engineering, Burton]

Summary

Authorization to execute Change Order No. 3 with Lagco, Inc. in the amount of $83,070.56 to adjust quantities to complete construction of Meadows/Northland/ Arlington Public Improvements Project, Phase 6B1 & 6B2. The increase brings the new Contract total to $2,855,950.20. Funds are Budgeted. (L0813-23) (Burton/Albright)

 

Budgetary Implications [select]: Yes

Advance Document Review:

Law: No

Risk Management:  No

Fully Budgeted [select]: Yes

Account Number:                     3120-303202-3211-91713                        $97,134.56

4003-303202-3223-91715                      ($14,064.00)

This Fiscal Year Impact:                     $83,070.56

Annual Impact:                      $

Project: CDBG_2023; MNA_PH6A_2019

Activity: C03; CONSTRUCT

Budget Reference: 2023; 2019

Current Balance:                      3120-303202-3211-91713 - $1,000,000.00

4003-303202-3223-91715 - $   565,566.28

 

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 3, which is attached hereto and incorporated herein by reference, to the Agreement with Lagco, Inc., for construction of the Meadows/Northland/Arlington Public Improvements Project, Phase 6B1 and 6B2, increasing the Contract price by the sum of $83,070.56, raising the total price to $2,855,950.20.

                     Section 2 - That an amount, not to exceed the sum of $83,070.56, be and hereby is approved for payment to Lagco, Inc., from account # 3120-303202-91713 ($97,134.56) and account # 4003-303202-91715 (-$14,064.00), pursuant to the terms of the Change Order and the Agreement.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                                                                                                                  ___                     _____                     

                                                                                                                                                   MAYOR

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

0813-23:ANB:X:\Cases\COMDEV\23-LE0001\LEG\00789674.DOCX