Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) (Final) to the Contract with Walter Martin Excavating, Inc. for the Cardinal Ln. Stormwater Improvements Project, increasing the contract price by the sum of $9,094.47 from $219,110.00 to $228,204.47. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No. 1 (FINAL) with Walter Martin Excavating Inc. for Cardinal Lane Storm Water Improvements. (L1150-13) (Martin/Moloney)
This is a request to execute Change Order No. 1 (FINAL) with Walter Martin Excavating Inc. for Cardinal Lane Storm Water Improvements for an amount of $9,094.97 to relocate and modify junction box. This increase brings the total new contract cost to $228,204.47. Funds are budgeted.
Budgetary Implications: Yes
Advance Document Review: Law/Risk Management
Fully Budgeted: YES
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $9,094.47
Annual Impact:
Project: CARDINAL_2012
Activity: CONSTRUCT
Budget Reference: 2012
Current Balance: Funds are encumbered
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. One (1) (Final), which is attached hereto and incorporated herein by reference, to the Contract with Walter Martin Excavating, Inc. for the Cardinal Lane Stormwater Improvements Project, increasing the contract price by the sum of $9,094.47 from $219,110.00 to $228,204.47.
Section 2 - That an amount, not to exceed the sum of $9,094.47, be and hereby is approved for payment to Walter Martin Excavating, Inc. from account # 4052-303204-9211, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL